THERE WERE TAKEN SEVERAL SURVEY ACTIONS OF WORKING CONDITIONS AT WORKS OF THERMOELECTRICAL PLANT LOCATED NEARBY BARKER, IN THE PROVINCE OF BUENOS AIRES
Within the framework of activities of National Programme on Management and Survey of Working Conditions, UOCRA, through its Department of Occupational Safety and Health (OSH) together with UOCRA Azul, there were taken several survey actions at Thermoelectrical Plant worksite. This Power Plant is being built in an area of 12 hectares, located on Route 80, thousand meters away from the intersection with route 74, towards Barker Town; and it will generate 138 MW. Presently, we are developing reorganization tasks, excavations, ready mixed concrete and laying of electrical lines. At the same time 2 Power Plant turbines are being adjusted. Also, we have relieved workers data of employment registration The aim of both actions is keeping track of working conditions for early detection of any breach and further adjustment, in the framework of Decree 911 and other standards; and on the other hand, census of workers for the purposes of observing compliance with Act 22,250 Activities were carried out among UOCRA Azul Union teams and UOCRA technical teams belonging to the Department of Occupational Safety and Health (OSH).